当尾矿库库底排水管强度不能满足坝体加高的承载要求,且无法进行加固或在使用过程中出现损坏迹象时,均应对其进行封堵。排水管的封堵位置与封堵长度关系到尾矿库的安全运行,必须高度重视,防止留下安全隐患。该文结合某矿山工程事故案例,提出了排水管封堵技术要求以及因排水管承载能力不足导致的事故处理方法,为类似尾矿库工程提供参考。
When the tailings pond bottom drainage pipeline's strength does not meet the bearing requirements of dam height increase and can not be reinforced,or in the process of use a sign of failure appears,plugging of the pipe-lines is necessary.The place of plugging and the plugging length are connected with the safe operation of the tailings pond,great importance should be attached to prevent potential safety hazard.This paper,based on the similar engineer-ing accident case,puts forward the requirements of drainage pipeline plugging technology and the treatment of resulting accidents from bearing deficiency,providing reference for similar projects.
参考文献
[1] | GB 50863-2013.尾矿设施设计规范[S].北京:中国计划出版社,2013. |
[2] | 李炜.水力计算手册[M].北京:中国水利电力出版社,2006 |
[3] | 长春黄金设计院 .栾川县启源矿业有限公司茄沟尾矿库(修改设计)变更说明书[R].长春:长春黄金设计院,2013. |