结合杏山铁矿露天转地下开采设计,介绍了杏山铁矿转地下开采过程中露天生产、挂帮矿体开采、深部矿体开采在时空关系、产量衔接、开拓系统、采矿方法、安全措施等方面的设计实践,技术方案值得借鉴.
Combining with the design of transferring open pit mining into underground mining in Xingshan iron mine, the paper introduces the design practice in the aspects of time-space relationship, production connection, de-velopment system, mining method and safety measures of openpit stoping, nearby-slope orebody and deep part ore-body mining in the process. The technical proposals are of great referrences.